Electrification of Budgam-Banihal railway track to be completed by Aug 15

Date:

Umaisar Gull Ganie

Srinagar, Jul 20 : The much-hyped electrification of Budgam to Banihal railway track is all set to be completed by August 15 while the authorities said that the work on the track is in full swing.

The project worth Rs 324 crore is almost in final stage, Additional General Manager, Indian Railway Construction Company Limited told the news agency—Kashmir News Observer (KNO), adding that the work on second phase of railway electrification in Kashmir from Budgam to Banihal sections would likely get completed by 15 August this year.

“We have already completed the first phase of the electrification process from Baramulla-Budgam sections and have also conducted trial runs in March this year as well,” he said, adding that the project with a route length of 137.73 kilometers have three main sub-stations of Qazigund, Budgam, and Baramulla.

The electricity for the sub stations are being provided by the Power Development Department (PDD) , he said that the electricity at two sub stations including Baramulla and Qazigund have been provided while the department is not able to provide electricity due to the hindrance by the locals. 

The project is all set to reduce the pollution and also saves 60 percent amount compared to the use of fuel, he said—(KNO)

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Popular

spot_imgspot_img

Subscribe

More like this
Related

J&K UT Govt. should review developmental indices of Backward areas: Shameem Bukhari

JKGCWF convenes crucial meeting of Kashmir valley at Srinagar SRINAGAR,...

Want to fill gaps created by shortcomings of teachers with technology: PM Modi

Prime Minister Narendra Modi on Friday said he wants...

Climate change: Modi says it’s time to redefine development metrics, promote green GDP

New Delhi, Mar 29 : Prime Minister Narendra Modi...

Amit Shah to campaign in Assam on April 6: Himanta

Guwahati, Mar 29 : Assam Chief Minister Himanta Biswa...