Vinod Bhat
New Delhi: Right now, about 100 feet below the Bandra Kurla Complex in Mumbai, a railway station is taking shape, deeper underground than a 10-storey building is tall.
A few kilometres away, a 3,200-tonne machine is grinding through rock beneath Thane Creek, boring India’s first undersea rail tunnel.
And across Gujarat, 371 km of completed viaduct already stands in the sky, with track bed laid and electrification masts coming up.

India’s first bullet train is no longer an announcement. It is 508 km of construction, moving at full pace. The first service begins in the last quarter of 2027!
This is the story of the Mumbai-Ahmedabad bullet train: the thinking behind it, the engineering inside it, and what it sets up for the decades ahead.
The power of one economy:
When you travel from Tokyo to Osaka on Japan’s high-speed railway, you pass through Nagoya, Kyoto and Kobe. Five powerful economies, stitched together by one train.
They stop being five separate economies. They become one large economy. It is not 1+1+1 = 3. It becomes 1+1+1 = 111!
Now bring that idea home. The bullet train will cover Ahmedabad to Mumbai in 1 hour 58 minutes, a journey that takes 8 to 9 hours by road today. A professional can leave home in the morning, finish a full day’s work in Mumbai, travel back hundreds of kilometres, and still be home in time for dinner with their children the same evening.
That is the real power of high-speed rail. Distance stops being a barrier. Mumbai, Thane, Vapi, Surat, Vadodara, Anand, Ahmedabad: vibrant, rapidly growing economies, becoming one.
Why India waited:
In 1950, railways carried 80% of India’s transport. Over the next six decades, that share fell to 27%. Of course, now it has inched back to 30%.
Why did this happen?
For decades, the railways received very little fresh investment. Small budget, debated every year and always short of funds. Tracks stayed congested. Passenger and goods trains kept fighting for the same line.
This changed in 2016, when PM Modi merged the railway budget with the general budget. The railways could finally plan long term. Investment grew many times over, and the bottlenecks of sixty years started getting removed, one by one.
High-speed rail was discussed for years. Studies were commissioned, announcements were made, but nothing moved on the ground.
The decisive moment came in September 2017, when PM Modi and the Government of Japan laid the foundation stone of the Mumbai-Ahmedabad High-Speed Rail. Japan offered its high-speed rail technology, a system that has run for over 60 years without a single passenger fatality.
Even then, the project could not start in Maharashtra for close to two and a half years, as state permissions and land did not come. Then COVID took away two more years. Full construction began in earnest in 2021.
So, when critics ask, “where is the bullet train?”, the honest answer is: serious construction is just five years old. And look at what five years have built!
Why a bullet train is genuinely hard:
Think of the car you drive.
At 80 kmph, you are in comfortable control. Try doing that at 150 kmph: the wind, the vibration, the grip on the steering, everything changes. Now think of 200. Think of 300. This corridor is designed for 350 kmph!
Kinetic energy grows with the square of speed. Double the speed, and the energy becomes four times. So, the current drawn from the overhead wire, the braking, the interaction between wheel and rail: every system becomes exponentially more demanding.
At these speeds, even air becomes an engineering problem. The tunnels, the train’s nose, everything must be designed for it. This is why only a handful of countries have built high-speed rail.
The first project is not just a line on the map. It is the absorption of an entire technology by an entire industry.
A new kind of railway, the dedicated elevated corridor:
We have seen what a dedicated corridor can do.
India built dedicated freight corridors, moved its cargo trains onto them, and the results followed: freight loading touched 1,670 million tonnes in 2025-26, and India became the second largest cargo-carrying railway in the world.
We are applying the same idea to passengers. A dedicated passenger corridor, and an elevated one.

Elevation is the key innovation. On an elevated corridor, there are no cattle on the track, no trespassing, no level crossings. The alignment can run in a straight line, and straight lines are what allow 350 kmph. It also barely touches the land below: farms and roads continue underneath the viaduct.
So, about 465 km of this 508 km corridor, over 90%, runs on viaduct in the sky. Design speed 350 kmph, operating speed 320 kmph.
The pace of construction:
As of September 2026,
- 456 km pier work & 371 km viaduct construction completed
- 6 lakh noise barriers installed along 299 km stretch
- 9,300 OHE masts installed across 206 km viaduct
- 4 mountain tunnels excavated & 5 km of the 21 km Maharashtra tunnel has been excavated by the mountain tunnelling method.
- Civil work completed at 8 stations. Architectural finishing work underway.
- Work is in progress at all three rolling stock depots at Sabarmati, Surat and Thane.

How did the speed come?
We used the Full Span Launching Method instead of conventional segmented girder method. Instead of casting a bridge span piece by piece, a complete 40-metre concrete girder, weighing 970 tonnes, is cast in a factory yard, carried to the site, and placed on the piers in one go. It is ten times faster than the conventional method.

The first few launching machines were imported. Then our engineers worked on the designs. Today, the giant cranes that lift more than 1,000 tonnes in a single movement are designed and manufactured in India.
The Japanese teams who visit the corridor are surprised at the pace of work. Some of the construction technologies developed here, they now want to take back to Japan for their own next corridor!
“Japan could not have done it at this speed,” remarked Masafumi Shukuri, Chairman of the International High-Speed Rail Association (IHRA).
Going under the sea:
In Maharashtra, the corridor runs through a 21 km tunnel, and 7 km of it passes under the sea, beneath Thane Creek. This is India’s first undersea rail tunnel.

Two Tunnel Boring Machines were launched in July 2026, from Vikhroli and Sawli. These are among the largest machines ever deployed in India.
Each has a cutterhead 13.6 metres in diameter, as tall as a 4-storey building. Each weigh over 3,000 tonnes, roughly 500 Asian elephants. The machine is 96 metres long, nearly five cricket pitches laid end to end!
A station 100 feet below Mumbai:
In the heart of Mumbai’s business district, at the Bandra Kurla Complex, we are building the only underground station on the corridor, and it is an engineering story of its own.
The excavation goes about 32 metres below ground level, the depth of a 10-storey building. Inside that pit, three levels are coming up: platforms, concourse and services. Six platforms, each over 400 metres long, built for full-length bullet trains.

Think of the challenge! A massive excavation in the middle of a dense, working business district, with towers, roads and metro lines all around.
Stations that belong to their cities:
The other eleven stations are elevated, and each one is designed around the character of its host city. Civil work is complete at eight stations, where architectural finishing is now underway.
Take Surat. For generations, Surat has been the city where the world’s diamonds are cut and polished. Its bullet train station is designed around that identity, with a facade inspired by the facets of a diamond. When the first service starts from Surat in 2027, the city of diamonds will also be the city where India’s high-speed journey began.
Or take Sabarmati, the corridor’s terminal in Ahmedabad. We are not building just a station there; we are building a multimodal transport hub.

Under one roof, the bullet train connects with the Indian Railways stations on both sides, the metro and the BRTS, all linked by foot overbridges and travellators.
Electrifying for 350 kmph:
High-speed electrification is a different game altogether.
At 350 kmph, the pantograph must collect electricity from the overhead wire without a single spark, interruption or fluctuation. So, every wire is installed under precisely calculated mechanical tension.
The system is an advanced 2×25 kV compound catenary, among the most sophisticated railway electrification technologies in the world, being deployed in India for the first time.
Nearly 22,000 steel masts will carry this network across the corridor. More than 9,300 of them are already up.

As the train moves from one power section to the next, the transition will happen without passengers even noticing it.
Making it at home:
Alongside the corridor, we are building the trains and the technology.
ICF and BEML are manufacturing the indigenous B28 trainset, designed for 280 kmph. The first body frame is complete and is undergoing structural testing. Track trials are expected by mid-2027. A faster B35, designed for 350 kmph, is the next step.
The fixed infrastructure is being indigenised too. All major transformers of the high-speed electrification system, the cross arms on the masts, the ground, protection and feeder wires: all are being manufactured in India.
The J-slab ballast less track, a Japanese high-speed technology, is being cast in Indian yards by Indian engineers, for the first time in India.
This is what technology absorption means. We are learning to build every part of the system, and manufacture it at home.
Safety systems:
The corridor is being fitted with 28 seismometers. The moment primary earthquake waves are detected, power shuts down automatically and trains brake to a safe stop.
Anemometers at 14 locations will measure wind speeds in real time. Rain gauges will track rainfall at vulnerable points. All of it feeds one Operation Control Centre, where protection systems respond in fractions of a second.
A template for future corridors:
The Mumbai-Ahmedabad project is our learning ground. The real goal is what comes after. We have standardised the construction philosophy for all future corridors:
- The foundation will be designed as per the exact soil of each spot. Everything above it, that is the pier, viaduct, track, station structure, electrification and signalling, will be standard.
- Standard subsystems can be manufactured in factories and assembled at site. This cuts construction time and improves quality.
- Common designs mean common spares, common training, common maintenance across corridors. Operating costs fall for the life of the network.
- Suppliers for future corridors will qualify under one common framework for quality, safety and reliability. On these parameters, there can be no compromise.
Seven more corridors:
The Union Budget 2026-27 has announced seven high-speed rail corridors as growth connectors, covering nearly 4,000 km, with expected investments of around ₹16 lakh crore.
Delhi to Lucknow in 2 hours 10 minutes.
Delhi to Varanasi in 3 hours 50 minutes.
Chennai to Bengaluru in 1 hour 13 minutes.
Mumbai to Pune in 48 minutes! People can travel back and forth twice a day, eat Vada Pav in Mumbai and Bakarwadi in Pune.
Bengaluru to Hyderabad, Chennai to Hyderabad, Pune to Hyderabad, and Varanasi to Patna to Siliguri complete the seven.
Every one of them will be built on the standards, the suppliers and the skills created by the first corridor. That is why the first one matters so much.
The first ride:
The first high-speed rail service will commence in 2027. The first section to open will be from Surat to Vapi. The full corridor to Mumbai follows in phases.
Today, thousands of our hardworking engineers, technicians and workers are building something India has never had before.
In 2027, come experience your first bullet train ride!