Progress of works at Dah, & Hanu, Projects monitored 

Date:

Leh, May 18: Secretary Power and New Renewable Energy (NRE) UT Ladakh, Ravinder Kumar visited the 9 MW Dah, 9 MW Hanu HEPs and 66 KV Dah-Hanu-Khaltsi Transmission Line Project to review and monitor the progress of the ongoing works.

Secretary Power reviewed the ongoing pace of works and accordingly directed the TKC Agency to improve the manpower deployment and utilize the maximum possible advantage of the present working season so that the twin projects of Dah and Hanu along with the 66 KV Transmission Line are completed by October 2022 within the final approved completion date.

The Secretary briefed that when completed, the twin projects with a total installed capacity of 18 MW will provide a clean source of power as a renewable energy source and therefore directed the Power Department to plan for meeting the power demand of Ladakh from these projects and reduce the dependence on the grid for power.

Chief Engineer Generation Ladakh, Chief Project Engineer, Hydel Generation Kargil, Executive Engineer CD Khaltsi and EPD Leh were also present during the project visit along with representatives of the Turn Key Contract (TKC) Agency M/s P&R Infra project and PMC M/s WAPCOS Ltd.

Also, the department was instructed to tightly review and monitor the manpower deployment by the agency and work progress

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Popular

spot_imgspot_img

Subscribe

More like this
Related

Buried under silt, Wular Lake’s lotus returns after decades

Sajid RainaBandipora, Jul 10 : After a gap of...

Tourist revival sparks new life in Kashmir’s Mughal Gardens

Srinagar, Jul 10 : With over 79 days after...

No Rajya Sabha representation for J&K since 2021

Srinagar, Jul 10 : Jammu & Kashmir has been...

RTI portal fully functional, operating without any technical disruptions: IT Deptt

Srinagar, July 10 : The Information Technology department has...