Directs Time-Bound Completion of Pending Works; Stresses Strict Safety Compliance.
Budgam;20 FEB: Deputy Commissioner Budgam, Dr. Bilal Mohi-ud-din Bhat, IAS, today chaired a detailed review meeting to assess the operational and safety-related infrastructure issues of NIFT Budgam at DC office complex budgam to ensure time-bound completion of all pending works.
The DC took stock of the overall physical progress of the campus, which is spread over 132 kanals of land provided by the Government, and comprises 22 planned buildings, of which 19 buildings are substantially complete.
He observed that despite significant progress, several critical components remain pending, hindering the full operationalization of the campus.
The DC reviewed agenda-wise issues in detail and issued the following directions:
Regarding HVAC Systems, the chair was informed that HVAC systems are malfunctioning in the Administrative Block, Academic Block, Girls’ Hostel, Guest House, Director’s Residence, and Residential Quarters, while installation and commissioning in the Boys’ Hostel remain pending.
The DC directed immediate technical inspection of all HVAC installations, rectification of faults, and time-bound commissioning to ensure proper heating and ventilation facilities across all buildings.
He emphasized that given the prevailing climatic conditions, functional HVAC systems are essential for academic functioning and residential comfort.
Regarding the Electrical Sub-Station, the dc was apprised that substation works, including panels, DG sets, and transformers under Packages 2 and 3, are incomplete.
The DC directed JK SIDCO and the concerned executing agency to expedite completion of all substation components and ensure reliable and uninterrupted power supply to the campus.
He instructed that necessary measures, including utilization of the contractor’s security deposits where required, be taken to avoid further delay.
Regarding the Sewage Treatment Plant (STP), the meeting was informed that key components such as the main control panel, sludge drying beds, pumps, and recycled water pipelines are yet to be installed and commissioned.
The DC stressed the environmental significance of a fully functional STP and directed immediate installation and commissioning of all pending components to ensure proper wastewater treatment and compliance with environmental norms.
He stated that sustainable infrastructure management is a priority and must not be compromised.
Regarding Accessibility (Divyang/PWD Facilities), it was noted that essential washroom accessories for Divyang facilities are missing in hostel buildings under Package-2.
The DC directed that all required accessibility provisions be installed without delay to ensure inclusivity and compliance with statutory norms for persons with disabilities.
He emphasized that public institutions must be fully accessible and barrier-free.
Regarding Elevators, it was informed that lift installation is in progress in five Staff Quarter buildings, while commissioning under Package-3 is pending.
The DC directed early completion and commissioning after proper safety inspections and certification to make residential quarters fully operational.
Regarding Fire Safety Systems, it was observed that fire-fighting and fire alarm systems remain incomplete, posing serious safety concerns.
The DC directed that no building shall be declared fully functional without complete fire safety compliance.
He ordered immediate completion, testing, and certification of fire safety installations to safeguard life and property.
Regarding UPS Installation, it was reported that installation of UPS systems in both hostels and the Guest House remains pending with no significant progress.
The DC directed the concerned agency to initiate immediate installation to ensure uninterrupted power backup for essential services and academic operations.
Regarding Finishing Works, it was informed that finishing works are pending in Associate Professor Quarters, Staff Quarter Type-2A, and the Community Centre.
The DC directed completion of all remaining works with strict quality control and adherence to approved standards.
During the meeting, the DC emphasised strict monitoring, enhanced coordination among executing agencies, and adherence to timelines.
He reiterated that the target completion date of 31st March 2026 for all pending works must be achieved without fail.
The DC directed submission of weekly progress reports to his office and warned that accountability will be fixed in case of undue delay or non-compliance.
The meeting was attended by JD planning budgam Javaid Ahmad Najar , JD NIFT, officials from JK SIDCO, engineers of executing agencies, and district officers concerned.